Century Wharf, Cardiff Bay |
|
 |
Sector |
Private Housing |
| Client |
Westbury Homes |
| Architect |
Wynn Thomas Gordon Lewis |
| Contractor |
Brunswick |
| Procurement |
Traditional |
| Program |
|
| Value |
£60 million |
| Our Role |
Value Engineering |
| Key Aspect |
Brownfield city centre site |
top >>
Kenavon Drive, Reading |
|
 |
Client |
M J Gleeson Group Plc |
| Architect |
B & R Partnership |
| Contractor |
M J Gleeson Group Plc |
| Procurement |
Design and Build |
| Program |
81 weeks |
| Value |
£11 million |
| Our Role |
Employers Agent, Quantity Surveyor, CDM Co-ordinator |
| Key Aspect |
Brownfield city centre site Housing Forum Demonstration Project |
top >>
| Princes House, Brighton, East Sussex |
|
 |
Sector |
Private Housing |
| Client |
Baron Homes Construction |
| Architect |
n/a |
| Contractor |
Bluestone plc |
| Procurement |
JCT without Quants |
| Program |
65 weeks |
| Value |
£3.5 million |
| Our Role |
Design, Quantity Surveyor, BuildingSurveyor, CDM Co-ordinator, Party Wall Surveyor, Contract Administrator |
| Key Aspect |
City centre refurbishment of listed building |
top >>
| Clivedon Court, Brighton |
|
 |
Sector |
Private Housing |
| Client |
Remus Property Management |
| Contractor |
A & F Pilbeam Ltd |
| Procurement |
Traditional |
| Program |
30 weeks |
| Value |
£500,000 (phased) |
| Our Role |
Designer, Contract Administrator, CDM Co-ordinator |
| Key Aspect |
Phased city centre refurbishment whilst premises in occupation |
top >>
 |
|
| |
| |
| |
| |
| |
| |
|