1-57 Homeleigh, Brighton |
|
 |
Sector |
Planned Maintenance Repairs |
| Client |
Remus Property Management |
| Contractor |
Coleman Hunt |
| Procurement |
Traditional |
| Program |
12 weeks |
| Value |
£80,000 |
| Our Role |
Contract Administrator, CDM Co-ordinator |
| Key Aspect |
Internal & external refurbishment works requiring close liaison with residents |
top >>
| 1-96 Cliveden Court, Brighton |
|
 |
Sector |
Planned Maintenance Repairs |
| Client |
Remus Property Management |
| Contractor |
A & F Pilbeam |
| Procurement |
Traditional |
| Program |
30 weeks |
| Value |
£500,000 phased |
| Our Role |
Contract Admin, CDM Co-ordinator |
| Key Aspect |
Tight programme, cyclical planned maintenance |
top >>
| Hampden Court 75 Chesswood Road, Worthing |
|
 |
Sector |
Planned Maintenance Repairs |
| Client |
Remus Property Management |
| Contractor |
Langleys |
| Procurement |
Traditional |
| Program |
10 weeks |
| Value |
£60,000 |
| Our Role |
Contract Admin, CDM Co-ordinator |
| Key Aspect |
Diagnostic analysis of defective roof covering and decking |
top >>
| Atlantic Court, Shoreham-By-Sea |
|
 |
Sector |
Planned Maintenance Repairs |
| Client |
Atlantic Court Residents Co Ltd |
| Contractor |
Yoldings Ltd |
| Procurement |
Tradiitional |
| Program |
40 weeks |
| Value |
£250,000 |
| Our Role |
Contract Administrator |
| Key Aspect |
Residents in occupation during works |
top >>
 |
|
| |
| |
| |
| |
| |
| |
|