Daewoo European Design HQ, Worthing, West Sussex |
|
 |
Sector |
Industrial |
| Client |
Daewoo |
| Architect |
Michael Cook Associates |
| Contractor |
Norwest Hoist |
| Procurement |
Management Contract |
| Program |
52 weeks |
| Value |
£10 million |
| Our Role |
Quantity Surveyor, CDM Co-ordinator, Project Manager |
| Key Aspect |
Fast track Management Contract to achieve key dates |
top >>
TA Centre, London |
|
 |
Sector |
Industrial |
| Client |
TAVRA |
| Architect |
BPR Architects Ltd |
| Contractor |
Lovells |
| Procurement |
JCT 80 |
| Program |
65 weeks |
| Value |
£3.5 million |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Price certainty at acceptance of tender |
top >>
| Courage Distribution Depot, Lewes, East Sussex |
|
 |
Sector |
Industrial |
| Client |
Grand Metropolitan |
| Architect |
APP Partnership |
| Contractor |
Birse Construction |
| Procurement |
Traditional |
| Program |
39 weeks |
| Value |
£2 milllion |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Economic resolution of ground works and infrastructure |
top >>
AV Trade, Albourne |
New Warehouse and Offices
|
|
 |
Sector |
Industrial |
| Client |
AVtrade Leasing Ltd |
| Contractor |
A & F Pilbeam |
| Procurement |
2 stage tender |
| Program |
10 months |
| Value |
£1.8 milllion |
| Our Role |
Quantity Surveyor, CDM Co-ordinator |
| Key Aspect |
Excavated material used to form lake
to avoid landfill charges |