Felbrigg House Care Home, Dover
12 room care home for adults with profound learning / mental health difficulties
 |
| Client |
Broadham Care Ltd |
| Contractor |
Rok |
| Procurement |
Negotiated |
| Programme |
6 months |
| Value |
£600,000 |
| Our Role |
Contract Administrator |
| Key Aspect |
TBA |
|
Farnham Hospital, Farnham
Community Hospital procured by PFI
 |
| Client |
Gleeson |
| Contractor |
Gleeson |
| Procurement |
PFI |
| Programme |
78 weeks |
| Value |
£15,000,000 |
| Our Role |
Consortium Quantity Surveyor |
| Key Aspect |
PFI |
|
Colwood Hospital, Car Park, Haywards Heath
Demolition of existing buildings and provision of a new surface car park
 |
| Client |
Brighton & Sussex University Hospital |
| Contractor |
Sunninghill Construction |
| Procurement |
GC Works – Schedules of Work |
| Programme |
22 weeks |
| Value |
£600,000 |
| Our Role |
Quantity Surveyor, CDM Co-ordinator |
| Key Aspect |
- Asbestos removal within existing buildings - Budget constraints - Programme linked to residential development |
|
Pax Hill, Farnham
98 bed new build care home
 |
| Client |
Bentley Care Homes |
| Contractor |
HA & DB Kitchen |
| Procurement |
Traditional Single Stage |
| Programme |
18 months |
| Value |
£6,500,000 |
| Our Role |
Bank Monitoring Surveyor |
| Key Aspect |
Risk management of complex design and Procurement method. |
|
Charles Barry Building, RSCH, Brighton
Phase 2 Refurbishment
 |
| Client |
Brighton & Sussex University Hospitals NHS Trust |
| Contractor |
Bluestone |
| Procurement |
Traditional |
| Programme |
52 weeks |
| Value |
£1,400,000 |
| Our Role |
CDM Co-ordinator, Quantity Surveyor, Building Surveyor, Contract Administrator |
| Key Aspect |
Uninterrupted use of building as works were carried out. |
|
Princess Royal Hospital, Haywards Heath
Roof Refurbishment
 |
| Client |
Brighton & Sussex University Hospitals NHS Trust |
| Contractor |
Trojan Rose |
| Procurement |
Traditional |
| Programme |
64 weeks |
| Value |
£980,000 |
| Our Role |
Lead Consultant and Designer |
| Key Aspect |
Re-design of roof details and liaison with statutory authorities. |
|
|