Kingsland Road, London
New build in 4 blocks for social, shared ownership and commercial units
 |
| Client |
Community Housing Association |
| Contractor |
Jestico & Whiles |
| Procurement |
Design and Build |
| Programme |
2 years |
| Value |
£12,500,000 |
| Our Role |
Employer’s Agent, Planning Supervisor |
| Key Aspect |
Mixed use |
|
Ebenezer Chapel, Brighton, East Sussex
Demolition of existing Chapel and construction of new Chapel, Community facilities and 49Nr affordable apartments
 |
| Client |
Hyde Housing Association |
| Contractor |
Denne Construction |
| Procurement |
Design and Build |
| Programme |
70 weeks |
| Value |
£6,600,000 |
| Our Role |
Employer’s Agent, CDM Co-ordinator, Cost Consultant, Eco-Homes Assessor, Party Wall Surveyor |
| Key Aspect |
Redevelopment of brownfield site which maximises provision of new residential accommodation combined with improvements to Chapel and Community facilities. |
|
Burndell Road, Yapton, Nr Arundel
Social housing development of 9 houses and 4 flats
 |
| Client |
Servite Houses |
| Contractor |
Cheesmur Building Contractors |
| Procurement |
JCT 05 with Contractor’s Design |
| Programme |
52 weeks |
| Value |
£1,354,000 |
| Our Role |
Employer's Agent, CDM Co-ordinator |
| Key Aspect |
Restricted site access and extensive site remediation work from previous use as garage since 1930. |
|
Charrington Court, Atlanta Boulevard, Romford
10 storey block of flats – mixed tenure, 24 general needs, 39 shared ownership, 35 private for sale
 |
| Client |
Community Housing Association |
| Contractor |
Mount Anvil plc |
| Procurement |
Design and Build |
| Programme |
98 weeks |
| Value |
£12,000,000 |
| Our Role |
Employer's Agent, Quantity Surveyor, CDM Co-ordinator |
| Key Aspect |
Off site manufacture of pods for kitchens, bathrooms and amenities, green roof - sedum |
|
Brighton Housing Trust, Brighton, East Sussex
Refurbishment of existing hall to provide a new day centre for homeless people
 |
| Client |
Brighton Housing Trust |
| Contractor |
Cheesmur Building Contractors |
| Procurement |
JCT IFC 2005 – Schedules of Work |
| Programme |
7 months |
| Value |
£600,000 |
| Our Role |
Quantity Surveyor, CDM Co-ordinator |
| Key Aspect |
- Very restricted budget - Listed building - Planning constraints leading to difficult cost control |
|
Arundel Road, Littlehampton, West Sussex
Social housing development of 24 flats
 |
| Client |
Servite Houses |
| Contractor |
Cheesmur Building Contractors |
| Procurement |
JCT 05 with Contractor’s Design |
| Programme |
54 weeks |
| Value |
£1,900,000 |
| Our Role |
Employer's Agents, CDM Co-ordinator |
| Key Aspect |
Construction of 24 flats in a prominent town centre location with restricted space and time constraints. |
|
Grays Inn Buildings, London
104 social housing units, new build and refurbishment
 |
| Client |
Community Housing Group |
| Contractor |
Allenbuild Ltd |
| Procurement |
PPC 2000 |
| Programme |
120 weeks |
| Value |
£16,500,000 |
| Our Role |
Client Representative, Planning Supervisor, Party Wall Surveyor, Quantity Surveyor |
| Key Aspect |
- Partnering Project PPC 2000 - Included additional work for fitting out shops and community facilities |
|
St Andrew’s Church, Fulham, London
Partial demolition of the existing Church to form a new 5-storey flat construction with 10 flats to be let out, new communal Church facilities and Church fit-out
 |
| Client |
Parochial Church Council |
| Contractor |
TBC |
| Procurement |
Traditional JCT Standard Building Contract with Quants 2005 Edition |
| Programme |
52 weeks |
| Value |
£2,500,000 |
| Our Role |
Quantity Surveyor, CDM Co-ordinator, Party Wall Surveyor |
| Key Aspect |
Managing funding from multiple sources including banks and community sources |
|
Stoke Abbott Road, Worthing, West Sussex
11 social housing units in self-contained block
 |
| Client |
Servite Houses |
| Contractor |
Cheesmurs |
| Procurement |
Design and Build |
| Programme |
38 Weeks |
| Value |
£680,000 |
| Our Role |
Employer's Agent, Party Wall Surveyor, CDM Co-ordinator |
| Key Aspect |
Continuation of existing developed site using Partnering principles |
|
Keymer Avenue, Peacehaven, Brighton
Development of 46 Nr houses and flats on two adjacent sites. New build rented and shared ownership.
 |
| Client |
Kelsey / Dominion Housing Association |
| Contractor |
Bovis Homes Ltd |
| Procurement |
Design and Build |
| Programme |
114 weeks |
| Value |
£3,000,000 |
| Our Role |
Employer's Agent |
| Key Aspect |
Carried out under Section 106 Agreement on part of a larger development by Bovis Homes |
|
|