St Dunstans, Brighton
Replacement roof, glazing and services to swimming pool
 |
| Client |
St Dunstans |
| Contractor |
Mansell Construction Services Ltd |
| Procurement |
Traditional |
| Programme |
45 weeks |
| Value |
£1,000,000 |
| Our Role |
Designer, Quantity Surveyor, Planning Supervisor |
| Key Aspect |
Re-cladding and upgrade of existing swimming pool |
|
Marina Pavilion, Hastings
Fit out of existing shell to create restaurant, meeting rooms and a health & beauty club
 |
| Client |
Seaspace |
| Contractor |
Chamelion |
| Procurement |
Design and Build |
| Programme |
5 months |
| Value |
£900,000 |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Fast track fit out project |
|
University of Sussex, Falmer, Brighton
Alterations and extensions to playing fields pavilion
 |
| Client |
University of Sussex |
| Contractor |
Frank Sandell & Son (Worthing) Ltd |
| Procurement |
Traditional |
| Programme |
24 weeks |
| Value |
£395,000 |
| Our Role |
Quantity Surveyor |
| Key Aspect |
New changing facilities |
|
Yellowave, Brighton
New all weather beach volley ball facility
 |
| Client |
Yellowave |
| Contractor |
Integra (Brighton) Ltd |
| Procurement |
Traditional |
| Programme |
6 months |
| Value |
£450,000 |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Unique facility and design, value engineered to achieve feasibility |
|
|