Budgens Supermarket, Heathfield, Sussex |
|
 |
Sector |
Disaster Recovery |
| Client |
Budgens Stores Ltd |
| Contractor |
Kingfisher |
| Procurement |
IFC 84 |
| Program |
15 weeks |
| Value |
£500,000 |
| Our Role |
Quantity Surveyor, Building Surveyor |
| Key Aspect |
Temporary refrigeration cabinets used to mitigate interruption |
top >>
| Avana Bakeries, Newport Wales |
|
 |
Sector |
Disaster Recovery |
| Client |
RHM Technology |
| Contractor |
Shepherd Design and Build |
| Procurement |
JCT Management Contract |
| Program |
18 months |
| Value |
£200,000 |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Business interruption limited to 2 weeks by sourcing alternative facility |
top >>
| Admiral Duncan, London |
|
 |
Sector |
Disaster Recovery |
| Client |
Scottish & Newcastle Retail |
| Contractor |
Horizon Building & Design Ltd |
| Procurement |
Minor works |
| Program |
5 weeks |
| Value |
£150,000 |
| Our Role |
Quantity Surveyor, Project Co-ordinator |
| Key Aspect |
Immediate response to minimise business interruption |
top >>
| Balcombe House, Balcombe |
Restoration following fire damage
|
|
 |
Sector |
Disaster Recovery |
| Client |
Wimshurst & Co |
| Contractor |
P D Harris |
| Procurement |
Tradiitional |
| Program |
52 weeks |
| Value |
£500,000 |
| Our Role |
Quantity Surveyor |
| Key Aspect |
Listed timber framed building |
top >>
 |
|
| |
| |
| |
| |
| |
| |
|